JUNE 14 2024 – HOMES ENGLAND ‘10,000 MASTERPLAN [IN 2019] – CRAWLEY WESTERN RELIEF ROAD [CWRR] + DELIVERY DATES, POLICY & PLANNING – MASTERPLAN DELAYED

HOMES ENGLAND ‘10,000’ MASTERPLAN [IN 2019]

Crawley Western Relief Road [CWRR]

Middle section delivered in partnership with Homes England

North and South sections delivered in partnership with the LPA’s [Local Planning Authorities] and Homes England

North section delivered working with Gatwick Airport

 

 

Infrastructure Delivery

2021 – Start first neighbourhood: CWRR middle section, flood alleviation works, services and education campus

2023 – First homes occupied, secondary school [6FE] and SEND facilities with sport pitches, local centre opens [first phase], Ifield Country Park and linear parks, invest in existing health centres and CWRR middle section opens

2025 – First primary school, local centre [second phase], secondary school expansion [8FE]

2029 – Local centre [third phase], health and well being centre and community centre

2031 – Second primary school

2033 – Secondary school complete 

Policy and Planning

2019 – CWRR safeguarded in Crawley Local Plan [Reg 18]

2019 – Start consultation

2019 – Building evidence base for west of Ifield

2020 – Horsham and Crawley Reg 19 Consultation

2020 – Outline planning application submitted for first neighbourhood

2021 – Horsham and Crawley Local Plans adopted

2023 – Market and affordable homes occupied in first neighbourhood

2026 – Horsham and Crawley Local Plans reviewed – delivery of second and third neighbourhood

 

JUNE 11 2024 – 3,000 OR 10,000 HOUSES WEST OF IFIELD – WHO IS TELLING THE TRUTH?